© 2024 Maine Public | Registered 501(c)(3) EIN: 22-3171529
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations
Scroll down to see all available streams.

Eversource Study Supports Using 'Jet Plow' To Bury Power Line Under Little Bay

The proposed Seacoast Reliability Project would include a mile of cable beneath Little Bay, center.
Eversource
The proposed Seacoast Reliability Project would include a mile of cable beneath Little Bay, center.
The proposed Seacoast Reliability Project would include a mile of cable beneath Little Bay, center.
Credit Eversource
The proposed Seacoast Reliability Project would include a mile of cable beneath Little Bay, center.

Eversource is doubling down on what it says will be the best way to run a new power line under the Seacoast's Little Bay. 

The transmission line known as the Seacoast Reliability Project is how Eversource wants to meet the mandates of New England’s electric grid operator.

First proposed in 2016, the project includes a mile of cable buried beneath Little Bay, between Durham and Newington.

Earlier this year, the state Site Evaluation Committee asked Eversource to study ways to bury that cable.

Potential methods include a process called jet plowing, where sediment is blown back as the line is laid, and horizontal directional drilling, where the cable is bored beneath the bay bottom.

Some stakeholders say drilling would stir up less sediment and impact the bay less.

Eversource's new study, released this week, counters that. It says jet plowing is less risky and more efficient, including fewer impacts to neighbors, and a far shorter and cheaper construction schedule.

The utility says jet plowing would take about 3 months and bring the project's cost to ratepayers to about $84 million. On the other hand, it says drilling would take 28 months and bring the cost to double that. 

The study also says both methods would temporarily stir up some sediment, with low environmental impacts overall. But it says drilling would require more on-land staging and disruption to neighbors, and could risk more serious accidents that would harm the bay. 

Other stakeholders may submit or request studies of their own as part of hearings on the project, which are set to begin in late August.

Read all the documents submitted as part of the Seacoast Reliability Project's state siting application.

Copyright 2021 New Hampshire Public Radio. To see more, visit .

Annie Ropeik joined NHPR’s reporting team in 2017, following stints with public radio stations and collaborations across the country. She has reported everywhere from fishing boats, island villages and cargo terminals in Alaska, to cornfields, factories and Superfund sites in the Midwest.