USS Alexandria Departs After Early Completion of Overhaul

KITTERY, Maine - Portsmouth Naval Shipyard has completed an overhaul of the attack submarine USS Alexandria two weeks early and $9 million under budget.

The Navy says it has a shortage of submarines, so it's important to minimize their time in dry dock. In this case, the overhaul was the fastest on a Los Angeles-class submarine in the Navy's history.

The Alexandria and its crew of 13 officers and 120 enlisted sailors departed last week. It had arrived in October 2013.

Capt. William Greene, the shipyard commander, said the project team "showed a commitment to safely delivering first-time quality work.'' Project Superintendent Scott Curtis said workers applied lessons learned from past overhauls to make this one a "record-setting early delivery.''